| Project Title |
Implementing
Organization |
Project
Status % |
Remarks |
| 09262-Primary Health Facilities |
|
|
|
| Design & Supervision of Kachikau Clinic |
Chobe D/Council |
100% |
Supervision is ongoing. |
| 09263- Rural Administration Centre |
|
|
|
| RAC Supervision |
MLG |
100% |
Supervision is ongoing. |
| Kasane RAC Extension – Construction |
MLG |
100% |
Project is complete and handed over on the 06/04/2011. |
| Procurement of furniture for the new RAC offices |
MLG |
100% |
Furniture has been delivered. |
| 09269- Municipal Services |
|
|
|
| Kasane Fire station Construction |
Chobe D/Council |
100% |
Contractor is currently on site attending to snags. |
| Kasane Fire station Supervision |
Chobe D/Council |
100% |
Supervision complete. |