North East District Council
Completed Projects
Project Title

 Implementing

Organization

 Project

Status %

 Remarks 
09259-Primary School Facilities
Construction of New primary at Tati Siding NEDC 100% Works complete.
Contractor attending to snags.
09262-Primary Health Facilities
Design and Documentation NEDC 100% Pre contract Services complete
09268- Village Infrastructure
Masunga Infrastructure Development Phase III -  Constructions NEDC 100% Contractor is currently attending to
defects list at the site offices
Ongoing Projects

Project Title

 Implementing

 Organization

 Project

 status %

 Remarks
09259-Primary School Facilities
Design and Documentation NEDC Design and Tender documentation complete.
Post contract consultancy NEDC Supervision Ongoing.
EIA & AIA Consultancy NEDC AIA and EIA approved. Pre-contract services
completed. Final report pending completion of
construction.
09262-Primary Health Facilities
Tati siding clinic expansion NEDC 92 % Phase 1 practically complete, building
handed over.
Staff and furniture relocated into phase 1  
Phase 2 at  92 % .
Post contract consultancy NEDC Consultant engaged and executing supervision
services for the clinic and clinic housing.
09265- Labour Intensive Works
Ipelegeng Programme NEDC 70% 11/12 project started and handling 64 projects
 (1No construction of LA 2 type house,
maintenance and grass cutting.
09268- Village Infrastructure
Construction of Masunga internal roads - Supervision NEDC 97% The Consultant supervision team is on site.
Construction of Masunga Street lighting - Supervision NEDC 7% Consultant has completed the Evaluation
 of the construction tenders and submitted
the evaluation report to council on
 the 31/05/2011.