Kweneng District Council
Completed Projects
Project Title Implementing Organisation

Project Status %

Remarks
09259-Primary School Facilities
Construction of Ramaphatle New Primary School Kweneng District Council 100% Complete and under defects liability period.
Construction of Education Facilities at Nkoyaphiri P School (2No. Classroom block) Kweneng District Council 100% Complete and under defects liability period.
Construction of Shadishadi RADs Hostels Kweneng District Council 100% Complete.
Construction of Education Facilities at Lesirane(Staff Houses) Kweneng District Council 100% Complete and under defects liability period.
Package-32: Kweneng: Facilities Backlog Eradication at - Boatlaname, Shadishadi, Sojwe, Diphuduhudu, Ngware, Hatsalatladi, Leologane, Botlhapatlou P/Schools Kweneng District Council 100% On liability period.
Package-43: Kweneng: Facilities Backlog Eradication Project - Medie, Lentsweletau, Ditshukudu, Mahetlwe, Dikgatlhong, Kgope, Makgasane P/Schools Kweneng District Council 100% Under defects liability period.
Package-2: Letlhakeng: Facilities backlog eradication at Gothibamang & Malwelwe P/Schools Kweneng District Council 100%
Package-24A: Kweneng: Facilities Backlog eradication at Tloaneng, Gabane, Gasiko, Pule Memorial and Mmonye P/Schools Kweneng District Council 100% On liability period.
Package-24B: Facilities backlog eradication at Letlole P/Schools Kweneng District Council 100% On liability period.
Package-24C: Facilities backlog eradication at Kumakwane P/Schools Kweneng District Council 100% On liability period.
09262-Primary Health Facilities
New  Health Post - Serinane Kweneng District Council 100% Complete.
Construction of 2 nurses houses at Gabane & Mogoditshane Kweneng District Council 100% Complete and under defects liability period.
Construction of Health Facilities at Tsolamosese Kweneng District Council 100% Complete and under defects liability period.
Construction of Tsetseng clinic Kweneng District Council 100% Complete
Construction of Health Facilities at Mmokolodi Kweneng District Council 100%
09267- Village Water Supply
Construction of elevated water tanks at Kweneng and Hatsalatladi Kweneng District Council 100% Project complete, Retention released
Kweneng/ Medie Interconnection scheme Kweneng District Council 100% Project complete, On defects liability.
Gakuto/ Mmatseta Interconnection scheme Kweneng District Council 100% Project complete, On defects liability.
Supply and Erection of Elevated Water tanks at Lephepe and Shadishadi Kweneng District Council 100% Project complete, Retention released
Maintenance of Gabane Transmission pipe line Kweneng District Council 100% Project complete, Retention released
Ongoing Projects

Project Title

 Implementting

Organization

 Project

Status %

 Remarks 
 Social Welfare Services
 Construction of 100 Destitute Houses Kweneng District Council 99% 96 house complete and handed over to beneficiaries;
 4 ongoing and substantially complete.
Maintenance of Ikago Centre Kweneng District Council 98% Practical completion stage
09259-Primary School Facilities
Tsolamosese-Lesirane Primary School (Expansion of Lesirane Primary School) Kweneng District Council 91% Non completion certificate issued to the contractor
and intention to determine.
Supply and Delivery of Gas Stoves Kweneng District Council
09265- Labour Intensive Works
Letlhakeng Sub District Kweneng District Council Project Addendum sent requesting additional funds.
MAA/ Lentsweletau Sub District Kweneng District Council Project Addendum sent requesting additional funds.
Mogoditshane/ Thamaga Sub District Kweneng District Council Project Addendum sent requesting additional funds.
09267- Village Water Supply
Kopong Rehabilitation Water Supply Scheme- Design Kweneng District Council 10% Inception report presented.
Upgrading of water supply  scheme Sorilatlholo Kweneng District Council 98% Finishing touches on village tank.
Upgrading of water supply  scheme Sesung Kweneng District Council 98% Finishing touches on village tank.
09268- Village Infrastructure
Construction of Thamaga Infrastructure Kweneng District Council 70% Contractor behind schedule.
Consultancy Services for Thamaga Infrastructure Kweneng District Council 70%
09274- Rural &Urban sanitation
Rehabilitation &dislodging of Molepolole sewerage ponds Kweneng District Council 55%