| Project Title |
Implementing
Organization |
Project
Status % |
Remarks |
| 09259-Primary School Facilities |
|
|
|
| Relocation of Linchwe Primary School |
KGTC |
100% |
|
Project handed over to council on 31 March 2010. Kitchen equipment fitting complete, left with electrical connection and testing. | |
| Consortium consultancy services-pre contract services for the construction of the proposed new Boseja primary school |
KGTC |
100% |
The pre contract services have been completed and the construction of this project has been shelved due to economic recession |
| 09262-Primary Health Facilities |
|
|
|
| Reconstruction & modification of Oodi clinic |
KGTC |
100% |
Project handed over to client on the 2nd December 2010. On defects liability period |
| Upgrading of Rasesa Clinic |
KGTC |
100% |
Project handed over to client in February 2010.On liability period |
| 09267- Village Water Supply |
|
|
|
| Construction of treatment plant at Dikgonnye |
KGTC |
100% |
Project handed over to client. On defects liability period |
| Consultancy services for the construction of water treatment plant at Dikgonnye |
KGTC |
100% |
Complete |
| River villages water supply rehabilitation |
KGTC |
100% |
Project handed over to client on the 22 December 2010. |
| Consultancy services for the water supply rehabilitation at the River Villages |
KGTC |
100% |
Complete |
| 09269- Municipal Services |
|
|
|
| Consultancy services on proposed fire station staff housing in Mochudi |
KGTC |
100% |
Supervision complete |
| Construction of Fire station staff houses (4X4 double storey flats) |
KGTC |
100% |
Complete.On liability period |
| 09273- District and Urban Roads |
|
|
|
| Construction of Lokgalo bridge along Leshibitse-Ratlhokwa |
KGTC |
100% |
Complete. Project handed over for client usage on the 2nd September 2010.Under liability period |
| Design Review And Supervision Of Lokgalo Bridge |
KGTC |
100% |
Supervision complete |
| Construction of Leshibitse-A1 junction road |
KGTC |
100% |
The project handed over on the 28th June 2011 and on liability period |
| Consultancy services on the construction of Leshibitse-A1 junction road |
KGTC |
100% |
Supervision is complete |