Kgatleng District Council
Completed Projects
Project Title

Implementing

Organization

Project

Status %

Remarks
09259-Primary School Facilities
Relocation of Linchwe Primary School KGTC 100%

Project handed over to council on 31 March 2010. Kitchen equipment fitting complete, left with electrical connection and testing.

 
Consortium consultancy services-pre contract services for the construction of the proposed new Boseja primary school KGTC 100% The pre contract services have been completed and the construction of this project has been shelved due to economic recession
09262-Primary Health Facilities
Reconstruction & modification of Oodi clinic KGTC 100% Project handed over to client on the 2nd December 2010. On defects liability period
Upgrading of Rasesa Clinic KGTC 100% Project handed over to client in February 2010.On liability period
09267- Village Water Supply
Construction of treatment plant at Dikgonnye KGTC 100% Project handed over to client. On defects liability period
Consultancy services for the construction of water treatment plant at Dikgonnye KGTC 100% Complete
River villages water supply rehabilitation KGTC 100% Project handed over to client on the 22 December 2010.
Consultancy services for the water supply rehabilitation at the River Villages KGTC 100% Complete
09269- Municipal Services
Consultancy services on proposed fire station staff housing in Mochudi KGTC 100% Supervision complete
Construction of Fire station staff houses (4X4 double storey flats) KGTC 100% Complete.On liability period
09273- District and Urban Roads
Construction of Lokgalo bridge along Leshibitse-Ratlhokwa KGTC 100% Complete. Project handed over for client usage on the 2nd September 2010.Under liability period
Design Review And Supervision Of Lokgalo Bridge KGTC 100% Supervision complete
Construction of Leshibitse-A1 junction road KGTC 100% The project handed over on the 28th June 2011 and on liability period
Consultancy services on the construction of Leshibitse-A1 junction road KGTC 100% Supervision is complete
Ongoing Projects

Project Title

 Implementing

Organization

 Project

 Status %

 Remarks
09259-Primary School Facilities
Procurement of furniture for Matsieng P.S KGTDC 98% Awaiting delivery of tables for the CCTV cameras and tables with round edges.
Package 7: Backlog eradication at Dikwididi, Kgabotshwene, Letsebe, Rankoa and Sikwane P Schools KGTDC Backlog still being evaluated.

09267- Village Water Supply

Design and upgrading of booster pump station at Oodi KGTDC
Construction of phase one of the Oodi booster pump station KGTDC
09268- Village Infrastructure
Construction of 18km Mochudi/Pilane roads KGTDC 99% The project is complete attending drainage works and roads are in use.
Consultancy services for construction supervision of Mochudi Pilane Internal Roads. KGTDC 99% Supervision ongoing in conjunction with construction.
09269- Municipal Services
Construction of Fire station KGTDC 96% The project has been handed over. The contractor is attending extra-works.
Construction supervision of Mochudi fire station KGTDC 96% Supervision contract terminated.Project now supervised in house.
09273- District and Urban Roads
Construction of Morwa/Mmapole forestry bridge and associated roads KGTDC 89% About 6.4km of the road is primed and 1km surfaced. The bridge is almost complete and the contractor is currently working on the parapets.
Construction supervision of Morwa/Mmapole forestry bridge and associated roads KGTDC 89% Supervision ongoing in conjunction with construction.