| Project Title |
Implementing
Organization |
Project
Status % |
Remarks |
| 09259-Primary School Facilities |
|
|
|
| Construction of Kuke RADS Hostels |
Ghanzi District Council |
62.5% |
Project terminated, retendered and has been awarded as below. |
| 09262-Primary Health Facilities |
|
|
|
| Upgrading of health post at Karakubis |
Ghanzi District Council |
51.16% |
Contract terminated and awarded as below. |
| Equipment for Morama clinic including standby generator |
Ghanzi District Council |
76.92% |
Awaiting delivery of equipment. |
| 09264- Remote Area Development Programme |
|
|
|
| Funds feasibility study( New Xade , East Hanahai, N/Xanagas) |
Ghanzi District Council |
29.61% |
Awarded on 03/04/08, contractor deserted site. The intention is do it in-house and this has been recommended to DDC . |
| Purchase of livestock for RADS beneficiaries and training of such. |
Ghanzi District Council |
95% |
Purchase of livestock has started and 92 remaining beneficiaries will each benefit15 goats. |
| 09265- Labour Intensive Works |
|
|
|
| Gantsi North Labour intensive public works 2010/11 |
Ghanzi District Council |
12% |
50 projects to be implemented,41 projects have started and are at different implementation stages.
|
| Gantsi South Labour intensive public works 2010/11 |
Ghanzi District Council |
10% |
40 projects to be implemented of which 38 have started. |
| 09267- Village Water Supply |
|
|
|
| Construction of water department offices at Charleshill |
Ghanzi District Council |
80.83% |
New contractor engaged. |
| Completion of Construction of water department offices at Charleshill |
Ghanzi District Council |
80% |
Contract terminated. The remaining works will be finished in house.
|
| Electrification of 9 boreholes in 5 villages |
Ghanzi District Council |
|
All the 9 boreholes have been electrified, Tender for supply of backup generators has been signed and this will remedy electrical faults experienced.
|
| 09268- Village Infrastructure |
|
|
|
| Construction of roads, storm water drainage and utility sleeves in C/Hill |
Ghanzi District Council |
80% |
35.46km of base layer has been completed out of which 33.15km has been primed and 30.59km first sealed (surfacing). Surfacing works progress was hampered by shortage of gas in the country.
|