Ghanzi District Council
Completed Projects

 

Project Title

 

Implementing

Organization

 

Project

Status %

 

Remarks

09259-Primary School Facilities
Retender for completion of Construction of Kuke RADS Hostels

Ghanzi District Council

100% Project is complete and awaiting release of retention.
09262-Primary Health Facilities 
Completion of construction of Upgrading of health post at  Karakubis
Ghanzi District Council 65% Project Completed and handed over on the 18th March 2011.
Construction of new clinic at Morama Ghanzi District Council 100% Contractor has attended snags. Retention released
Ambulance at Morama clinic Ghanzi District Council 100% Ambulance delivered
09263- Rural Administration Centre
Cousultancy of council chamber Ghanzi District Council 100%
Construction of council chamber Ghanzi District Council 100% Complete.Handed over on the 10th November 2010.Retention released on the 24th August 2011.
09267- Village Water Supply
Installation of prepaid standpipes in Kole and Ncojane Ghanzi District Council 100% The project is complete.
09268- Village Infrastructure
Consultancy services for Ghanzi  Phase II infrastructure Ghanzi District Council 113.64%
Ghanzi Phase 2 infrastructure; Construction of tarred internal roads, utility sleeves and bus rank in Ghanzi township. Ghanzi District Council 112.65% Project handed over to the user department and
retention has been released on the 24 August 2011.
Consultancy supervision of tarred roads, storm water drainage and utility sleeves in C/Hill. Ghanzi District Council 122.18% Supervision going on well.
Ongoing Projects

Project Title

Implementing

Organization

 Project

 Status %

 Remarks
09259-Primary School Facilities
Construction of Kuke RADS Hostels Ghanzi District Council 62.5% Project terminated, retendered and has been awarded as below.
09262-Primary Health Facilities
Upgrading of health post at  Karakubis Ghanzi District Council 51.16% Contract terminated and awarded as below.
Equipment for Morama clinic including standby generator Ghanzi District Council 76.92% Awaiting delivery of equipment.
09264- Remote Area Development Programme
Funds feasibility study( New Xade , East Hanahai, N/Xanagas) Ghanzi District Council 29.61% Awarded on 03/04/08, contractor deserted site. The intention is do it in-house
and this has been recommended to DDC
.
Purchase of livestock for RADS beneficiaries and training of such. Ghanzi District Council 95% Purchase of livestock has started and 92 remaining beneficiaries will each benefit15 goats.
09265- Labour Intensive Works
Gantsi North Labour intensive public works 2010/11 Ghanzi District Council 12% 50 projects to be implemented,41 projects have started and
are at different implementation stages.
Gantsi South Labour intensive public works 2010/11 Ghanzi District Council 10% 40 projects to be implemented of which 38 have started.
09267- Village Water Supply
Construction of water department offices at Charleshill Ghanzi District Council 80.83% New contractor engaged.
Completion of Construction of water department offices at Charleshill Ghanzi District Council 80% Contract terminated.
The remaining works will be finished in house.
Electrification of 9 boreholes in 5 villages Ghanzi District Council All the 9 boreholes have been electrified,
Tender for supply of backup generators has been signed and this will remedy electrical faults experienced.
09268- Village Infrastructure
Construction of roads, storm water drainage and utility sleeves in C/Hill Ghanzi District Council 80% 35.46km of base layer has been completed out of which 33.15km has been primed and 30.59km first sealed (surfacing).
Surfacing works progress was hampered by shortage of gas
 in the country.